The UK G98 Form Your Installer Must Send Within 28 Days

EcoFlow

Many homeowners never see the paperwork that tells their distribution network operator (DNO) that they have installed solar panels and battery storage. This paperwork is the G98 form that your installer uses to notify the DNO about your installation within 28 days of commissioning.

This guide looks at:

  • What a G98 form is and why your solar installation project needs one

  • Where to find the G98 form download and who fills it in

  • The information your installer needs for the G98 commissioning form

  • Common G98 form mistakes that delay your paperwork

  • How to send and confirm your DNO has your G98 form

  • Making G98 form details easier to get right with compatible home energy storage

 A homeowner looking at a UK G98 form

What Is a G98 Form and Why Does Your UK Solar Install Need One?

What Is a G98 Form?

A G98 form is a notification that tells your local DNO about small generation and storage connected to the low-voltage network at your home. So, what is a G98 form in practice? A short record of what you have installed and when it went live. It applies to fully type-tested equipment up to 16A per phase. Plenty of people hunt for G98 form solar panels advice, but the notification also covers batteries, alone or alongside solar—so battery-only installs are included.

Why Does Your UK Solar Install Need One?

Your system needs a G98 form because it gives the DNO an accurate record of what is connected to its local network. With that record, the DNO can plan and manage the network safely. Your installer must submit it within 28 days of commissioning. For you, the G98 solar form doubles as a compliance record—one that may be requested at a house sale, by an insurer or by a future installer.

What Does a G98 Form Look Like?

Most people asking what does a G98 form look like expect something complicated. It isn't. The layout runs in a set order:

  • Installer and contact details

  • Property address

  • Installation type (generation, storage or both)

  • Equipment details

  • Commissioning date

  • Type-test reference

  • A signed declaration

Reading a G98 form example before your installer submits yours helps you spot gaps early. But always view the real thing on the ENA or your DNO's website, not a copy from a third party.

Where to Find the G98 Form Download and Who Fills It In

Getting the Latest ENA G98 Form

The Energy Networks Association (ENA) is the official source for Engineering Recommendation G98, and its website carries the current version of the notification form. Each DNO also runs its own portal or G98 form online submission, so check which one covers your address. Be wary of old PDFs on forums or installer websites—searches like G98 form UK Power Networks often surface outdated copies. Any G98 form download should come directly from the ENA or your DNO and be the current version.

Note: Form versions and submission routes can change. Always check the ENA website and your own DNO's website for the latest version.

Who Is Responsible for Completing the G98 DNO Form?

Your installer completes and submits the G98 DNO form, usually the MCS-certified installer where the job is covered by the Microgeneration Certification Scheme. Your role is smaller but real. You confirm the property details, hand over any equipment documents and ask for a copy. Ask for the MCS certification G98 form paperwork together, since the certificate and the notification are separate documents.

Some installers call the paperwork the G98/DNO form, so don't be thrown by the name. A hardwired battery or hybrid system fitted by a registered electrician still needs notifying—even when no solar is involved.

The Information Your Installer Needs for the G98 Commissioning Form

Property and Installation Details

The G98 commissioning form starts with the basics. Your installer enters your property address, their own company and contact details, and the installation type—generation, storage or both. They also record the commissioning date, which starts the 28-day clock, and the phase configuration (single or three-phase). Check the address matches your electricity bill, because a mismatch is an easy way to trigger queries.

Equipment Details the DNO Expects

Your installer also provides the equipment details, including:

  • The inverter manufacturer and model

  • Rated power output

  • Maximum current output

  • Total generation capacity

  • Phase configuration

  • Type-test reference

These details are necessary for your DNO to determine that your installed system is within the G98 limit. If you exceed the limit, you will face the G98 G99 form questions, meaning you have to follow the G99 application route.

Example 1, a New Solar-Plus-Storage Install with EcoFlow STREAM 5000

Let’s consider a solar installation with the EcoFlow STREAM 5000, which has four MPPT inputs at up to 1,250W each, giving a 5,000W maximum PV input and a 5,024Wh battery capacity. The unit also has up to 3,000W grid-tied output. The output power and current are filled in the equipment section, and the storage capacity is declared alongside the generation.

At 230V, 3,000W works out at roughly 13A on one phase. Your installer uses the exact figure from the data sheet. The inverter’s AC output matters in G98 application, not the panel wattage. The G98 form example data shows why it's important to get all relevant data early to save time.

Example 2, Adding Storage to Existing Solar with STREAM AC 5000

Let’s look at a second G98 form example data for a household that already has installed solar panels and wants to add storage. Before starting the installation, your installer checks your existing solar inverter make, model, rated output, current and type-test reference. Then, he creates a whole picture by assessing your existing inverter and retrofit storage, let’s say the EcoFlow STREAM AC 5000, grid-tied output. The EcoFlow STREAM AC 5000 has a grid tied output of 2,500W and 3,000W with an expansion battery.

If your current inverter is rated at 3,000W, then the installer will add the 2,500W of the battery, bringing the figure to 5,500W. This is about 24A on a single phase, meaning you can’t use the G98 application because it's above the limit. Instead, you have to follow the G99 application process.

G98 Form Sample Equipment Information Checklist

Use this simple checklist to ensure your G98 commissioning form is accurate:

  • Inverter make and model

  • Rated power (W)

  • Maximum output current (A)

  • Phases (single or three-phase)

  • Battery capacity (kWh)

  • Existing inverter details, if you already have solar

  • Type-test reference

  • Commissioning date

  • Installer MCS number

If any line is blank, ask why before the system goes live.

4 Common G98 Form Mistakes That Delay Your Paperwork

Most guides stop at "use the latest form". These are the less obvious errors that can lead to rejected notifications or rework.

1. Adding a Battery Without Rechecking the Combined 16A Limit

The mistake is treating storage as separate from your existing solar and checking each against the limit on its own. It is costly because the combined installation is what counts. If the total goes over 16A per phase, it can move out of the G98 route and need DNO approval before it is energised. Avoid it by adding the existing inverter and the battery's grid-tied output together at the design stage, before ordering anything.

2. Declaring the Wrong Phase on a Three-Phase Supply

Avoid the urge to list equipment as single-phase without showing which phase they connect to. Also, avoid stacking multiple units in a single phase. In the G98 form application, the total capacity is assessed per phase. Attempting either option can create an unbalanced layout which can break the rules even if the system is within the set limits. Record the phase for every inverter and battery unit. Then spread them deliberately.

3. Quoting a Type-Test Reference That Doesn't Match Your Exact Model

Installers sometimes copy a reference for a similar model, a different power rating or an earlier version of the same product. The DNO then cannot match the equipment to its register, which can mean queries and resubmission. Take the reference from the exact model number on the unit's data plate. Then compare it with the entry on the ENA Type Test Register.

4. Upgrading Later Without Updating the Notification

If you add solar panels, expansion batteries, and inverters in the future, the original form becomes invalid because your DNO’s records won’t match what is connected. Many homeowners make the mistake of assuming that original documentation is still valid. Upgrading the system might surpass the set limits which means you need to follow the G99 application process. If you plan to upgrade your system, ask your installer to reassess and re-notify your DNO before any change in capacity. Also, keep every version of the paperwork.

Sending the G98 Form and Confirming Your DNO Has It

Where to Send the Completed Documents

Where your G98 form goes depends on your DNO. UK Power Networks covers London, the South East and the East of England, and a search for the G98 form UK Power Networks route leads to its own pages with the current UK Power Networks G98 form. National Grid Electricity Distribution covers the Midlands, the South West and South Wales, and the National Grid G98 form goes through its connections portal. Some operators accept a G98 form online through a portal, while Electricity North West takes completed forms by email.

Your installer should know the right route—but ask which one they used.

Note: Each DNO can change its submission method. Confirm the current process on the DNO's website or through the ENA before anything is sent.

How Homeowners Can Confirm the Installer Notified the DNO

Start by asking your installer for the submission confirmation or reference and a copy of the completed form. Then check it sits in your handover pack next to the MCS certificate where relevant—the MCS certification G98 form paperwork should travel together. File your G98 solar form alongside the Electrical Installation Certificate too.

Nothing there? Contact the installer first. Still nothing? Contact the DNO directly with your address and MPAN (the meter number on your electricity bill), and quote any UK Power Networks G98 form or National Grid G98 form reference you hold.

Making G98 Form Details Easier to Get Right

Keeping New Solar and Storage Figures in One Place

Scattered equipment details across several products leave room for errors on your G98 form. Modern solar panels and storage batteries provide clear unit specifications to limit these errors. For example, EcoFlow STREAM 5000 combines four MPPT inputs, up to 5,000W PV input and 5,024Wh of storage in one unit. Your installer can then pull the numbers from a single set of specifications. As with any home battery in the UK, it is hardwired by a registered electrician.

EcoFlow STREAM 5000
Save an estimated £ 903 per year; results vary by household 5kWh storage with 100% usable capacity, no waste Powers kettles, dryers and more with up to 3000W output Connect up to 12 solar panels with 5000W solar input Expand from 5kWh up to 90kWh as needs grow Intelligent mode charges when cheap, discharges when prices peak 10,000 charge cycles backed by a 10-year warranty Compact design with 40% smaller footprint than comparable 5kWh systems 45.4kg body with a built-in handle for easier placement during installation IP65-rated for indoor or outdoor use, from -20°C to 55°C Keep essentials running during power cuts 15 protection layers plus proactive overload safeguards Hardwired installation by a registered electrician required in the UK

Adding a Battery Without Losing Track of Your Existing Inverter

Forgetting the existing inverter when storage is added later is an easy way to end up with an inaccurate form. For example, EcoFlow STREAM AC 5000 is designed to add storage to existing solar, which is a different job from a full solar-plus-storage install. Your installer can document the existing inverter and the battery's grid-tied output side by side. It is hardwired by a registered electrician too, which gives you a natural moment to ask for your existing paperwork.

EcoFlow STREAM AC 5000
Save an estimated £ 221 per year; results vary by household 5kWh capacity powers your home from day into night 100% usable capacity, so no stored energy goes to waste Up to 3000W off-grid output for kettles, dryers, stoves, and more Expandable up to 90kWh as your energy needs grow Smart modes use weather and tariffs to cut your bills Backup power during outages for appliances on the AC outlet Compact 44.6kg body designed to fit into spaces around the home IP65-rated for indoor or outdoor installation 40% smaller footprint than comparable 5kWh batteries Built to last: 10,000 cycles and 10-year warranty Control and track your savings from the EcoFlow app Installation by a certified electrician required in the UK 3000W output with expansion battery; single unit delivers 2500W

Conclusion

A properly completed G98 form ensures your UK home energy installation remains compliant with the set rules and safely registered with your local DNO. Your installer is the one who handles the submission—which must be done within 28 days of commissioning. As a home owner, you may be wondering if the installer handles the process, why should I know about the G98 commissioning form? You should know about this because you are responsible for ensuring your property complies with the grid regulations to prevent legal, financial, and practical headaches.

To use the G98 process, ensure your equipment stays within the set 16A per-phase limit, if not you are faced with the G98 G99 form headaches. Request your installer to give you a copy of the submitted G98 DNO form, MCS and electrical certificates for future upgrades, insurers or property sales.

G98 Form Frequently Asked Questions

How much is a G98 application?

A G98 application is free. However, fees and rules can change, therefore confirm with your DNO or check Ofgem and ENA official websites for up-to-date information before your installer submits your application.

How long does it take to get a G98?

Your installer has 28 days from commissioning to notify. DNO acknowledgement then usually takes a few working days to a couple of weeks, depending on the operator. You don't wait for permission before switching on.

What is the difference between G98 and G99?

solar panels

Do I need DNO approval for solar panels?

For G98 form solar panels installs within 16A per phase, you notify after commissioning, with no approval first. Above that limit, G99 means applying and waiting for DNO approval before the system is energised.

Is a G98 the same as a DNO?

No. G98 is the standard and the notification process, which is why some installers talk about a G98/DNO form. The DNO is the network operator that receiv