How to Make Your UK G98 Application Without the Stress

EcoFlow

You have invested in and installed solar panels and battery storage on your home. And now a grid-connection form from your local DNO is the obstacle between you and the switch-on. The good news is that for most UK homes, the G98 application is a simple process because it is a notify-and-connect. It’s not a wait-for-approval, and it’s usually free. The real problem you may face is missing the 28-day notification window, assuming every system qualifies, or underestimating how a battery or inverter affects the assessment.

This guide looks at:

  • What a G98 notification is and who qualifies

  • The difference between a G98 and a G99 solar application

  • How to submit a G98 application online with your DNO

  • Two UK installation scenarios that shape your G98 application

  • When your UK installation needs a G99 application instead

  • How to solve the biggest G98 application headaches with home energy storage

A G98 application is for installations below 16A per phase

What a G98 Application Means for UK Homes With Solar and Batteries

What a G98 Application Is and Who Needs One

A G98 application is the notification your installer sends to your local Distribution Network Operator (DNO) after connecting a small generation system, such as solar panels or a home battery. The name comes from the Energy Networks Association’s (ENA) Engineering Recommendation G98, which replaced the older G83.

It exists so the DNO knows what is connected to its network. It is not a permission request and it covers domestic solar inverters, microinverters and battery systems that stay within the G98 limit.

Your installer normally files it, so you may never touch the paperwork. But you should still know what it covers. It’s your supply, and you’re the one chasing answers if the notification never went in.

Who Qualifies Under the 16A per Phase Rule

G98 covers generation up to 16A per phase. If you are on a single-phase home supply, it’s about 3.68kW and if you are on three-phase it’s about 11.04kW. Your equipment is also type-tested and listed on the ENA Type Test Register.

If a unit isn’t listed, you can’t use the G98 notify-and-connect process, because such equipment requires additional compliance evidence, pushing you to the G99 application process. G98 is a notification to your DNO and is not a permission request, which means you connect first then tell them afterwards.

Note: Thresholds and procedures can change. Stay up-to-date using the ENA, Ofgem and your DNO’s official websites regarding the rules.

Why Batteries Count Toward Your Limit

Storage that can export power to the grid is treated as generation. Your battery isn’t exempt just because it sits quietly on a garage wall.

The assessment is based on inverter output in kW, not battery size in kWh. A 5kWh battery behind a 2.5kW inverter counts as 2.5kW. And the total installed generation at your property is counted, not just one device.

The Difference Between a G98 and a G99 Solar Application

Notify After or Approve Before With a G98 or G99 Application

The difference between a G98 and a G99 solar application comes down to timing and permission. Under G98, you connect, commission, then notify your DNO within 28 days of commissioning. Under G99, you apply, wait for DNO approval, then install.

G99 is for generation above 16A per phase. So if you’re weighing up a G98 or G99 application, this table shows where each one lands.

G98 vs G99 in the UK

G98 vs G99 in the UK

Feature

G98 application

G99 application

Governing standard

ENA Engineering Recommendation G98

ENA Engineering Recommendation G99

Type of process

Notification (connect and notify)

Application for approval (apply and wait)

Single-phase threshold

Up to 16A per phase (about 3.68kW)

Above 16A per phase (above about 3.68kW)

Three-phase threshold

Up to 16A per phase (about 11.04kW)

Above 16A per phase (above about 11.04kW)

Order of work

Install, commission, then notify

Apply, wait for DNO approval, then install

DNO approval before installation

No

Yes

Network study by the DNO

Not required

Often required, depending on size and location

Equipment

Type-tested, on the ENA Type Test Register

Non-standard equipment needs extra evidence

Typical cost

Usually free

Varies by DNO and system size; may carry a fee

Battery storage

Allowed if combined export stays within the limit

Needed if a battery can export above the limit

Note: Costs, timescales and DNO processes vary by network and can change. Check the ENA and your DNO’s website for current information.

How Inverter Capacity and Existing Equipment Change the Assessment

Your DNO considers the combined inverter and export capability. If you have a large solar array and a small inverter the assessment process is different to if you had the same array and a larger inverter.

Existing panel inverters are added to any new battery inverter, so a system that qualifies today isn’t guaranteed to qualify after an upgrade. A hard export limit may keep a project within G98, but your DNO has to accept it. That’s where G100 comes in which sets rules for Customer Limitation Schemes (CLS) to cap how much electricity a household can export to or import from the grid. The G100 helps prevent local grid overload and lets your home connect or expand faster without waiting for costly network upgrades. A DNO G98 application backed by a G100 limiter is a conversation with your network operator, not an assumption.

How to Submit a G98 Application Online With Your DNO

Finding the Right G98 Application Form

The G98 application form is the document your installer completes to notify your network operator. Most installers now submit a G98 application form online through ENA Connect Direct. DNO portals and the ENA G98 application form are fallbacks, and a G98 application form PDF still turns up on some network sites.

Which DNO is yours? A National Grid G98 application usually means National Grid Electricity Distribution, covering the Midlands, South West and Wales. Elsewhere, a UK Power Networks G98 application form applies to London, the South East and the East of England. The other operators are SSEN, Electricity North West, Northern Powergrid and SP Energy Networks.

Check yours using the MPAN on your electricity bill or the ENA’s postcode lookup.

G98 Application Cost and What Your Installer Needs to Supply

G98 application cost is normally nil. DNOs don’t usually charge to receive a notification for a compliant domestic system. What takes effort is gathering the details.

The DNO G98 application form asks for installer and installation details, the inverter and battery model, the type-test reference and the system capacity. Your installer usually files on your behalf. Ask for the submission reference anyway. Sending a G98 application online leaves a record you can point to later.

Note: Fees and requirements can change. Always check your DNO’s website and the ENA for the latest position.

Two UK Installation Scenarios That Shape Your G98 Application

Homes With No Solar Panels Yet

A new solar-plus-storage system is designed as one package. The inverter, panel array and export limit can be matched to 3.68kW per phase from day one.

A large PV array can sit alongside a smaller grid-export rating, because panel input and export are different numbers. A 5kW array feeding a 3.68kW-limited inverter can still stay within G98, provided the equipment is type-tested. So talk to your installer early, before any equipment is chosen, and ask for the export figure in writing to ensure a straightforward G98 application process.

Homes Adding a Battery to Existing Panels

Adding a retrofit battery to your existing solar setup means that its output is added to the existing solar inverter’s output. For example, if you have a 3.6kW solar inverter and you add a 2.5kW battery exporting at full output, then the total is 6.1kW. This figure is above the 3.68kW G98 application limits and pushes your installation to the G99 process, unless you limit the export and your DNO accepts it.

Therefore, check the original MCS certificate and commissioning documents to know what was registered. If your solar panels kit went through a National Grid G98 application or your own region’s equivalent, that record tells your installer what already counts toward your limit.

When Your UK Installation Needs a G99 Application Instead

A G99 isn’t a failure. It’s the route for systems the notification process wasn’t built for. These four situations cover the common triggers.

Solar Inverters or Arrays Above 16A per Phase

If your solar project has a total inverter output above 16A per phase, then you are routed to the G99 process. On a single-phase supply, that’s above 3.68kW and 11.04kW on a three-phase. A typical example is a larger array with a 5kW inverter on a single-phase supply. Panel size alone doesn’t decide it. The inverter’s AC output does.

Batteries That Can Export Above the Limit

A battery set to export more than 3.68kW per phase pushes the project into G99. A battery that only supplies your home, with no export above the limit, doesn’t trigger it in the same way.

It goes back to the inverter-rating point from earlier: assessment is by kW output, not kWh capacity. So ask what your battery’s inverter can export, not how much it stores.

Combined Capacity Across Several Devices

The DNO adds up everything at your property: the solar inverter, the battery inverter and any other generation. A 3.6kW solar inverter plus a 2.5kW battery can exceed the limit once combined.

A hard export limit may keep the project on G98 if your DNO accepts it. That’s the G100 route mentioned earlier. Without it, the combined figure decides.

Equipment That Isn’t Type-Tested

If you are installing equipment missing from the ENA Type Register, such as non-standard and older equipment, you can’t use the G98 process. These equipment usually require extra evidence, hence the G99 route. Therefore, check the register before buying the unit.

Solving the Biggest G98 Application Headaches With the Right Set-Up

The earlier worries come down to two things: matching equipment to the limit, and getting the installation done properly.

Sizing a New Solar and Battery System Around Your Grid Limit

The hardest part of installing your solar setup and storage from scratch is matching the equipment to the limit. A home battery like the EcoFlow STREAM 5000 accepts up to 5,000W of solar input and stores 5.024kWh. Its grid-tied output is rated at 3,000W, which is below the 3.68kW single-phase ceiling. This gap between solar input and export is what your installer checks before submitting your G98 application. It is hardwired, so a registered electrician handles installation, and the paperwork can be settled during that same visit.

EcoFlow STREAM 5000
Save an estimated £ 903 per year; results vary by household 5kWh storage with 100% usable capacity, no waste Powers kettles, dryers and more with up to 3000W output Connect up to 12 solar panels with 5000W solar input Expand from 5kWh up to 90kWh as needs grow Intelligent mode charges when cheap, discharges when prices peak 10,000 charge cycles backed by a 10-year warranty Compact design with 40% smaller footprint than comparable 5kWh systems 45.4kg body with a built-in handle for easier placement during installation IP65-rated for indoor or outdoor use, from -20°C to 55°C Keep essentials running during power cuts 15 protection layers plus proactive overload safeguards Hardwired installation by a registered electrician required in the UK

Adding Storage to Existing Panels Without Exceeding Your Limit

If you have already installed solar panels and you are worried that adding a battery may push them over the line, then the EcoFlow STREAM AC 5000 can help you stay within the set limits. This AC-coupled unit connects to your existing inverter which means you don’t have to replace it. It also has a 5.024kWh capacity, and a grid-tied output of 2500W. Your installer adds this value to your current inverter’s output to check whether the G98 application process still applies. If you have a typical 3.6kW inverter, then the total passes the 3.68kW limit, so ask about limiting. A registered electrician hardwires it, and the optional Smart Meter Dual CT adds overload protection.

EcoFlow STREAM AC 5000
Save an estimated £ 221 per year; results vary by household 5kWh capacity powers your home from day into night 100% usable capacity, so no stored energy goes to waste Up to 3000W off-grid output for kettles, dryers, stoves, and more Expandable up to 90kWh as your energy needs grow Smart modes use weather and tariffs to cut your bills Backup power during outages for appliances on the AC outlet Compact 44.6kg body designed to fit into spaces around the home IP65-rated for indoor or outdoor installation 40% smaller footprint than comparable 5kWh batteries Built to last: 10,000 cycles and 10-year warranty Control and track your savings from the EcoFlow app Installation by a certified electrician required in the UK 3000W output with expansion battery; single unit delivers 2500W

Conclusion

A G98 application is a notify-after process for systems within 16A per phase. Your installer must handle the application within 28 days of commissioning. The G99 process is for projects with over the 16A per phase limit. Inverter capacity, export settings and existing equipment determine which notification process is relevant to your project. And the G98 application cost is usually nothing, so the only real price of getting it wrong is time.

Talk to a registered installer, and your DNO where needed, before you buy anything. Settle the paperwork route first and the rest follows. You’ve done the hard part already, the form just needs to land in the right place. Ready to plan a system that fits your grid limit? Explore EcoFlow’s STREAM range to see which set-up suits your home.

Frequently Asked Questions About G98 Application

Do I Need a G98 Certificate?

You need a G98 notification—sometimes referred to as a G98 certificate/paperwork—when you connect a generation or storage system in your home. Your installer issues commissioning documentation, and the DNO acknowledges the notification. Keep both. The details on your DNO G98 application form should match the commissioning paperwork, and you’ll want it all if you sell or extend your system.

How Long Does It Take to Get a G98?

Your DNO usually processes and confirms the notification within 24–48 hours to 20 working days. However, your installer must notify them within 28 days of commissioning your solar installation. Once your installer submits the ENA G98 application form, ask for a reference and check your DNO’s service standards.

Is a G98 the Same as a DNO?

No. G98 is the ENA’s engineering standard for small-scale generation. The DNO is the regional company that runs your local electricity network and receives your notification. G98 is the rule; the DNO is who you tell.

Can I Track My DNO Application?

Yes. You can track using your installer or portal, local DNO or through a DNO Acceptance Letter.

Can a G99 Application Be Refused?

Yes. A DNO can refuse or restrict an application where the local network lacks capacity, voltage or fault-level headroom. The alternatives are reduced capacity, export limitation or network reinforcement, which can carry costs. Speaking to your installer early reduces the chance of an unwelcome surprise.